June 3, 2024 (30 minutes) Claims for Differing Site Conditions:
Type 1: subsurface or latent physical conditions at the site differing materially from those indicated in this Contract.
Type 2: Unknown physical conditions at the site of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in this Contract.
Procedures for filing DSC claims in a timely manner